A bathroom refurbishment, stage by stage

Mark
Sep 13
6 min read

The stages of a bathroom refurbishment run in a fixed order on site: strip-out, frame and first fix, making good the walls where needed, tiling, second fix, then the clean-down. Pipes and frames go in before the walls are made good because the walls and tiles close over them, and fittings come last because they fix onto finished tiles. The stages below are shown on several of our jobs, not one room start to finish. If you're planning a bathroom refurbishment, this is the order to expect. At strip-out the old suite and tiles come out, and it's the dustiest part, so read how to protect the rest of the house before work starts.

Strip-out, then the frame for a wall-hung toilet

Concealed cistern frame fixed inside a timber stud frame, walls and floor stripped bare before any tiling
The cistern frame sits inside a timber stud frame while the walls and floor are still bare.

The first thing to go back into a stripped bathroom is the metal frame for a wall-hung toilet, because the pan and the boxing are both set out from where it stands. Here it sits inside a timber stud frame running the full width of the wall: the metal carries the toilet, the timber carries the boxing and shelf. The two threaded rods with red caps will hold the pan, and once the boxing is tiled they can't be moved without opening it up, so ask for any change while the frame is still bare. Once the wall is finished, this frame is what sits behind a wall-hung toilet, which matters if one ever leaks.

Where a toilet can go depends on the waste, since a soil pipe needs a steady fall to the stack, and here the black waste outlet at the foot of the frame joins the old soil pipe on the right. Move it far from the old spot and more floor comes up. The finished room in the cover photo shows what a frame like this becomes: a tiled box with a shelf and the flush button set into it.

Tiling around the first-fix pipework

Large-format wall tiles going up on levelling clips with red wedges, with pipe stubs and valves coming through the tiles
Wall tiles going up around the first fix: pipe stubs already through, floor tiles already down.

The copper and white waste stubs on this job came through the wall before the tiles went up, which is what first fix means in a bathroom and why the tiler cuts around each one. Large-format tiles are going up on two walls, with the copper stubs and valves low on the left and, on the back wall, a pair of valves beside the white waste stub, while the floor tiles are already down and the wall above is still stripped to old plaster. A stub for an exposed fitting has to land where the cover plate of that fitting can hide the cut, because that plate is a set size and won't cover a ragged hole.

If you're choosing large tiles, ask your fitter to set out the first fix with the tile size in mind. The clear clips and red wedges hold the edges of big tiles flush while the adhesive sets, and how levelling clips and uncoupling mats keep tiles flat explains the method. When the old tiles come off, the adhesive often pulls the plaster face away with them, and loose or hollow plaster is your cue to ask what the new ones will go onto.

Second fix: the enclosure and the towel rail go on the finished walls

Chrome towel rail on navy metro tiles, painted wall above, next to a framed shower enclosure on a tray
Towel rail and enclosure fitted after tiling; the rail's valves and lower brackets go through the navy tiles.

A shower enclosure and a towel rail fix through finished surfaces rather than behind them, so they wait until the navy tiles are grouted and the painted wall above is done. Here the chrome rail's lower brackets and valves come through the tiles; its upper brackets sit on the paintwork. The enclosure's frame is screwed to the marble-effect tiles inside the shower. Each fixing is a hole through a finished face, and a cracked tile has to be cut out, so keep a few spares from your order.

The rail's valves only meet the pipes if those were set at the right centres before tiling. A rail bought later may not fit. Choose your towel rail before the first fix and give your fitter the pipe centres from its instructions.

Basins and furniture once the floor is down

Double vanity unit with two countertop basins and tall deck-mounted mixer taps, fitting instructions still on the top
A double vanity mid-fit: basins and taps on the stone top, fitting instructions still beside them.

Basins and furniture go in once the floor is finished, because a unit like this double vanity stands on the finished floor and its taps feed down through the stone top to pipework already waiting in the wall. This shaker-style one is mid-fit, with two countertop basins, tall deck-mounted mixers and the fitting instructions still on the top. With deck-mounted taps, flexible tails usually drop through the stone and join the first-fix stubs inside the cupboard. That works only if the unit's back can be cut around the stubs. If you've picked a unit, get its dimensions to your fitter before the pipes go in.

Unlike a built-in bath, which goes in before the wall tiles around it, a freestanding bath comes in near the end, onto a finished floor. If you're torn, decide before the first fix, because its waste and taps have to be planned before any tile is laid.

Brassware and the bath screen: the last fittings on the wall

Brass-framed bath screen and brushed brass shower column just fitted over a tiled bath, protection board on the floor
Bath screen and shower column just fitted, with the floor protection still down.

The bath screen and the shower column are the last fittings to go on a tiled wall, because they fix through tiles that have to be finished first, and brushed brass marks easily if other work is still going on around it. In this bathroom we had just fitted the brass-framed screen beside the column, with its rain head, handset, thermostatic riser and bath spout. The built-in bath has its side tiled in the same dark marble-effect tile as the walls, and a protection board is still down beside it. Pick your brassware before tiling starts anyway, because the pipe centres for a column are set at first fix.

If your tiles are sound and you still like them, swapping only the white sanitaryware skips the frame and tiling stages. Ask whether the new pieces suit the existing pipe positions, because if they don't, tiles come off anyway.

The same bathroom, cleaned down and finished

The same brass bath screen and shower column after the clean-down, dark marble-effect wall tiles
The same screen and shower column after the clean-down, with the glass and bath clean.

The last stage is the clean-down and snagging, and this same bathroom shows why it comes last: film and boards hide marks from fitting until they come off. Compared with the photo above, the bath is clean and the glass is clear. Walk the room with the lights on and look along the tiles and silicone lines from a low angle. On dark tiles like these, grout haze shows far more than on white, so ask how it will be cleaned off.

Before you plan your own refit, count which of these stages it really touches: a new layout means all of them, a like-for-like swap far fewer. Then talk to us about your bathroom.

Questions people ask before a bathroom refit

 Freestanding bath on marble-effect floor tiles, wall-mounted bath shower mixer, navy metro tiles behind
A freestanding bath in another bathroom: it stands on finished floor tiles, so the floor goes down first.

Do you tile before or after fitting the bath and toilet?

Both. A built-in bath goes in first so the wall tiles finish onto its rim and its panel can be tiled to match, as in this article's cover photo. The freestanding bath pictured above went onto finished floor tiles, but its mixer is on the wall, so those pipes were set before the wall was tiled. Settle early whether the wall tiles stop on the rim or run down behind it, as that changes how the joint is sealed. A wall-hung toilet goes on after the tiles, because its pan hangs on rods that come through the finished wall.

What does second fix mean in a bathroom?

Second fix is everything you see and use once the walls are done, like the pan on its frame and the taps on their pipes; first fix is the pipework and frames hidden behind the tiles. If a part can come off with a screwdriver without breaking a tile, it belongs to second fix.

Can I still use the toilet while the bathroom is being refurbished?

Not in the room being refitted, because the toilet comes off at strip-out and goes back on at second fix, after the tiling. If it's your only WC, raise that before work starts and ask your contractor how they'll handle it, because reconnecting the old pan as a stopgap isn't always practical with a given layout.

Comments


Ready to Get Started?

​

👉 [Click Here to Contact Us] 

📧 Questions? Email us at Contactusm4@gmail.com — we’re happy to help.

Craftsmanship You Can See. Results You Can Trust.

We take pride in transforming spaces through high-quality workmanship and attention to detail. Here’s a look at some of our recent residential painting and decorating projects:

56D655D6-43C6-45E2-B3B8-68960935AD37-removebg-preview.avif

M4 Property Maintenance delivers high-quality painting, decorating, handyman services, plumbing repairs, bathroom upgrades and complete property maintenance across Virginia Water and surrounding areas.

Quick Links

Service Areas

Address

Location

Went worth Estate

Ascot

Virginia Water

Maidenhead

Windsor

Sunningdale

Sunninghill

M4 Property maintenance

Phone +447948510090

Email - contactusm4@gmail.com

​​

Privacy Policy

Cookie Policy

bottom of page